ZENITH Tower A3
3Basement + Ground + 21 + Terrace
   Steps of construction:
 1- Mobilization (period: 20 days)
 2-
Shoring (period: 1 month)
 3- Excavation (
period: 4 months)
 
 
   Step Mobilization
 
Construction Plants ,Temporary access to site ,Site Survey ,Electrical Power  ,Lighting ,Water  ,Site Offices for Staffs ,Site Administration  ,Security ,Temporary Telephones ,Rest Room for workers ,Stores ,Temporary Latrines & Ablutions for workers ,Site Fencing ,Temporary Gates ,Site Sign Boards ,Site Safety.
 
  Step Shoring
  Generally for shoring works Boring Rigs Machined is used for drilling holes and Steel Casing & Concrete are inserted with the help of Crawling Cranes.


 
Step Excavation
  Excavation of 12 meters will be done in order to maintain a Depth for 3 basements underneath the building. Excavation will be carried with the help of Machinery like Excavator, Dozing Machine, Tippers, and Wheel Loaders for shifting rumbles
 
 

zenith



zenith

zenith

Pictures of start of construction


ZENITH A3
1/9/2009

zenith a3

zenith a3

zenith a3

zenith a3

zenith a3

sports city


  home l customer service l sports city l about us
zenith tower, ali entezam ,hassan jahed pari, karim jahed pari, zenith tower,ZENITH TOWER,zenith tower real eatate,zenith tower,zenith tower,dubai sports city,sports city,zenith,zenith towers,dubai sports city,sports city,zenith tower,ali entezam,jahed pari,zenith towers

Visited the site <